Our Projects

Ardenta Tower

Client

Client

PT. Semesta Development

PT. Semesta Development
Year

Year

2022

2022
Duration

Duration

12 Weeks

12 Weeks
Location

Location

Jakarta

Jakarta

Challenge:

PT. Semesta Development needed the structural steel frame for a 22-floor mixed-use tower completed without disrupting the tight downtown Jakarta site access. Crane time and street closures were limited to overnight windows.

Materials:

High-tensile structural steel beams, moment-resisting steel connections, seismic-rated bracing

Approach:

We pre-fabricated frame sections off-site to reduce on-site welding time, then scheduled installation in overnight shifts coordinated with the city's street-closure permits. Engineering validated every connection for the tower's seismic load requirements before fabrication began.

PT. Semesta Development

"They worked around our site constraints without ever slowing the schedule down."